Today, July 6, 2023, the Danube Bridge - Tulcea/Brăila, an important infrastructure project in Romania, was officially inaugurated, as announced on the Ministry of Transport's Facebook page by Mr. Ionel Scărișoreanu, Secretary of State in the Ministry of Transport.
Here are the technical details of this investment project:
Brăila - Jijila section (Phase I) has a length of 19 km and is equipped with two lanes in each direction, merging lanes, shoulders, a median zone, and guardrails.
DN22 Smârdan - Măcin connection road (Phase 2) has a length of 4.3 km and is equipped with one lane in each direction. The connection road starts from km 7+940 of the main road (Brăila-Jijila) and intersects with DN22 Smârdan-Măcin.
The main works provided for in the contract:
-Suspended bridge over the Danube -2 access viaducts -1 viaduct over the railway -23.4 km of road works (roads) -35 bridges, passages and minor structures -86 footbridges -9 road junctions and roundabouts -1 Maintenance Center and Coordination -1 toll station
More information:
- it is designed to have a lifespan of 120 years; - it has a monitoring and control center that will permanently record the state of the bridge, through the 30 sensors installed on the bridge at essential points; - for this structure, the most complex and advanced test project of a bridge in Romania was carried out; - at this bridge, a dehumidification system will work for all bridge assemblies, including the metal deck and cables. The cables are insulated on the outside with a protection that ensures tightness, and the air inside will be permanently dehumidified and monitored, so as to ensure an anti-corrosive environment; - to ensure durability and high anti-corrosion protection, the metal deck is also dehumidified inside, certain longitudinal stiffeners being used as channels for the distribution of dehumidified air in the internal space of the deck, and a system of sensors will monitor the maintenance of the humidity state from the box below levels that cause oxidation. The relative humidity will be maintained below 90% to prevent corrosion and to allow circulation on the bridge in urgently, in any season; - the bridge is equipped with sidewalks, but they will be used strictly for its maintenance and will not be open to public pedestrian traffic; -no bridge crossing fee is paid in the first 5 years.
The initial value of the project is 1,995,932,260 RON, without VAT, financed from non-refundable external funds, and the builder is Asociea Astaldi S.P.A. - IHI Infrastructure System Co. Ltd.
In the first stage, road traffic will be opened on the partial connection, with unloading in Tulcea county on the road to Măcin (stage I), and then the option to Jijila (stage II) will be completed as soon as possible.